New York Contractor Deposit Rules: What Happens to Your Money Before the Work Is Done?

New York does not cap how much a contractor can ask for up front. Instead, the law controls where the money goes: every payment made before the work is substantially complete must be held in an escrow account at a New York bank, or covered by a bond, until it is earned under your contract's payment schedule.

Sources: New York General Business Law section 771 and Lien Law section 71-a. Last verified: .

In California instead? See the California deposit limits page.

New York deadlines and thresholds at a glance

Sources: General Business Law section 771; Lien Law section 71-a; NYC DCWP for the $200 license threshold.
What must happenDeadline or threshold
Written contract requiredJobs over $500
Payments deposited into a New York escrow accountWithin 5 business days of receipt
Owner told in writing where the money is held (if the contract does not name the bank)Within 10 business days
Bond, indemnity contract, or letter of credit delivered instead of escrowWithin 10 business days of payment
Owner may cancel the signed contract in writingUntil midnight of the third business day after signing
NYC license requiredJobs over $200 (DCWP)

Check your New York contract

Six questions. Each one matches a protection New York law gives you.

New York contract checklist

Answer yes or no for your contract. You will see which protections are present and what to ask for if one is missing.

My contract is in writing and signed by both sides.
It includes a payment schedule in dollars and cents tied to stages of completion.
It says where my payments will be held in escrow, or names a bond or letter of credit instead.
It includes the mechanic's lien notice.
It includes a Notice of Cancellation (3 business days).
I verified the contractor's license, where my area requires one.

Based on New York General Business Law section 771 and Lien Law section 71-a. The checklist runs in your browser. Nothing you enter is sent anywhere.

How does the escrow rule protect you?

New York does not limit the size of a deposit. It controls where the money sits until the work earns it.

Every payment a contractor receives before the work is substantially complete must go into an escrow account at a bank located in New York within 5 business days. If the contract does not name the bank, the contractor must tell you in writing where the money is held within 10 business days. Money in escrow remains your property until it is properly applied to the job.

The alternative: a bond or letter of credit

Instead of escrow, the contractor may give you a bond, a contract of indemnity, or an irrevocable letter of credit that guarantees the return or proper application of your payments, within 10 business days of receiving the money. Your contract must tell you which protection applies.

When the contractor can take money out of escrow

Only in one of these situations, and then only up to the contractor's reasonable costs:

Your payments are trust funds

Payments you make for a home improvement are trust funds under Lien Law Article 3-A. They are not the contractor's money to spend on other jobs. Your deposit is legally your money until the work earns it.

Sources: Lien Law section 71-a(4) and Article 3-A; General Business Law section 771(1)(e).

What are the rules for progress payments in New York?

If your contract calls for payments before the work is substantially complete, it must include a schedule. The schedule shows each payment in dollars and cents and the stage of completion it pays for, including materials to be supplied.

Each progress payment must bear a reasonable relationship to the work performed, the materials purchased, or the expenses the contractor is obligated for at that time.

Example

On a $40,000 renovation, a schedule asking for $20,000 before any work is performed does not bear a reasonable relationship to work done or materials bought. A lawful schedule ties each payment, in dollars and cents, to a stage of completion.

What your written contract must include

New York requires a written contract for home improvement jobs over $500. These state rules apply to contractors whose home improvement contracts total more than $1,500 in any 12 months. The contract must be signed by both of you, and you must get a copy before work begins. It must include:

The mechanic's lien notice must appear in clear and conspicuous bold type. It warns that any contractor, subcontractor, or material supplier who is not paid may have a claim against your property known as a mechanic's lien, and that paying the agreed price before a lien is filed may invalidate the lien.

You can cancel the contract in writing until midnight of the third business day after you sign.

Source: General Business Law section 771, including section 771(1)(f).

What changes in New York City?

In New York City, a Home Improvement Contractor license from the Department of Consumer and Worker Protection (DCWP) is required for residential home improvement work costing more than $200.

DCWP's consumer guidance advises paying no more than 25% of the total contract amount up front. That figure is city consumer guidance, not a state law. The state sets no cap, and the escrow rule still applies to whatever you pay.

Verify a contractor's license at nyc.gov/dcwp or by calling 311. If a DCWP licensed contractor owes you money, you may be eligible for reimbursement through the Home Improvement Contractor Trust Fund.

Outside New York City

New York State does not license home improvement contractors. New York City and Suffolk, Nassau, Westchester, Putnam, and Rockland counties do, according to the New York Attorney General.

Sources: NYC DCWP, Home Improvement Contractor Tips (PDF); New York Attorney General, Home Improvement Fact Sheet.

What to do if your money was not protected

Start by asking in writing where your payments are held. You can send this sentence to your contractor:

Under New York Lien Law section 71-a, please tell me in writing where my payments are being held in escrow, or provide the bond or letter of credit covering them.

Where to complain

If you want a second set of eyes, CostCheckGPT is being built to flag the payment schedule and escrow terms in a bid or contract against these rules.

Questions homeowners ask

Is there a maximum contractor deposit in New York?

No. State law sets no dollar or percentage cap on a home improvement down payment. The protection is the escrow or bond requirement and the rule that progress payments must reasonably match the work.

Where does my deposit have to go?

Into an escrow account at a bank in New York within 5 business days, unless the contractor instead delivers a bond, a contract of indemnity, or an irrevocable letter of credit within 10 business days.

How do I find out where my money is held?

If the contract does not name the bank, the contractor must tell you in writing within 10 business days of receiving the payment. Ask in writing if you have not been told.

When can the contractor take money out of escrow?

Under the payment schedule in your contract, when the job is substantially complete, or if you violate the contract, and then only up to the contractor's reasonable costs.

How much can a contractor ask for up front in New York City?

DCWP, the city licensing agency, advises homeowners to pay no more than 25% of the total contract amount up front. That is city consumer guidance; the state itself sets no cap, and the escrow rule still applies to whatever is paid.

Can I cancel a home improvement contract after signing?

Yes, in writing, until midnight of the third business day after you sign. The contract must include a Notice of Cancellation explaining this.

Does my contractor need a license?

New York State does not license home improvement contractors, but New York City and Suffolk, Nassau, Westchester, Putnam, and Rockland counties do. In NYC, a DCWP license is required for residential work over $200.

What should a New York home improvement contract include?

For jobs over $500, a signed written contract with the contractor's information and license number if applicable, start and completion dates, a description of the work and materials, the total price, a payment schedule tied to stages of completion, the mechanic's lien notice, the escrow notice, and the cancellation notice.

Methodology and sources

This page states the deposit and payment rules in New York General Business Law Article 36-A (sections 770 and 771), Lien Law section 71-a and Article 3-A, New York Attorney General home improvement guidance, and NYC DCWP consumer guidance. Every rule on the page comes from these sources:

  1. New York General Business Law section 771 (statute text)
  2. New York Lien Law section 71-a (statute text)
  3. New York Attorney General, Home Improvement Fact Sheet
  4. NYC DCWP, Home Improvement Contractor Tips (PDF)
  5. NYC DCWP license check: nyc.gov/dcwp or 311

Last verified: . We re-check this page against the statute every quarter.

General information about New York law, not legal advice.